The rule in plain words
The item "Impact of volatility adjustment set to zero" reported in Impact of long-term guarantees measures and transitionals (S.22.01) must be equal to the difference between the value of "Without volatility adjustment and without transitional measures" and the value of "Without transitional on interest rate"
The headline gives only the template and the kind of check, because the rule is too long to say in a headline. The plain words above say all of it.
This is a blocking check. A return that fails it is normally rejected, so fix it before you submit. It runs only when your filing indicators mark S.22.01 as reported.
The cells it reads
Impact of long-term guarantees measures and transitionals (S.22.01.01.01)
Rows
- R0100Eligible own funds to meet Minimum Capital Requirement
- R0110Minimum Capital Requirement
Columns
- C0040Without transitional on interest rate
- C0060Without volatility adjustment and without transitional measures
- C0070Impact of volatility adjustment set to zero
Which returns it applies to
Line4 Check runs it on annual solo (ARS) and annual branch (ARB) returns on EIOPA taxonomy 2.10.0. EIOPA applies it to annual branch (ARB), annual solo (ARS), annual ECB solo (AES) and annual ECB branch (AEB) returns, as a blocking check.
EIOPA’s own words and formula
In EIOPA’s list of validations, word for word:
The item "Impact of volatility adjustment set to zero" reported in S.22.01 - Impact of long-term guarantees measures and transitionals must be equal to the difference between the value of "Without volatility adjustment and without transitional measures" and the value of "Without transitional on interest rate".
Show the formulaShowHide
EIOPA's formula. Cells are written as {t: table, r: row, c: column}.
{t: S.22.01.01.01, c: C0070, z: Z0001} = {t: S.22.01.01.01, c: C0060, z: Z0001} - {t: S.22.01.01.01, c: C0040, z: Z0001}Other rules on Impact of long-term guarantees measures and transitionals (S.22.01)
- Impact of long-term guarantees measures and transitionals: values must agree (BV852)Blocking
- Impact of long-term guarantees measures and transitionals: values must agree (BV854)Blocking
- Impact of long-term guarantees measures and transitionals: values must agree (BV855)Blocking
- Impact of long-term guarantees measures and transitionals and own funds: a total must equal the sum of its parts (BV850)Blocking
- Impact of long-term guarantees measures and transitionals: values must agree (BV848)Blocking
- Impact of long-term guarantees measures and transitionals: values must agree (BV847)Blocking
- Impact of long-term guarantees measures and transitionals and solvency capital requirement - for undertakings using an internal model (partial or full): two values must match (BV872)Blocking
- Impact of long-term guarantees measures and transitionals and minimum capital requirement - only life or only non-life insurance or reinsurance activity: a conditional check (BV916)Blocking
Every Solvency II rule on S.22.01
Checks like this one, run at the point of submission, are the first step to real-time supervision. Line4 builds SupTech software for financial regulators that runs checks like these as each return arrives.