The rule in plain words
The item "Eligible own funds to meet the SCR" reported in Impact of long-term guarantees measures and transitionals (S.22.01) must be equal to the sum of the "Tier I", "Tier II" and "Tier III"
The headline gives only the template and the kind of check, because the rule is too long to say in a headline. The plain words above say all of it.
EIOPA writes it out as separate checks, one for each table or return it covers. Line4 Check runs two of them (BV63-1 and BV63-2), and a failure names the one that failed.
What to do if your return fails it
- 01Open the tables below and find the cells the rule reads.
- 02Add up the parts in your return and compare the result with the total.
- 03If they differ, a part is missing, a value sits in the wrong cell, or the total is out of date.
- 04EIOPA allows a small rounding difference, worked out from the decimals each value is reported with.
- 05It runs only when your filing indicators mark S.22.01 as reported.
- 06This is a blocking check. A return that fails it is normally rejected, so fix it before you submit.
The cells it reads
Impact of long-term guarantees measures and transitionals (S.22.01.01.01)
Rows
- R0050Eligible own funds to meet Solvency Capital Requirement
- R0060Tier 1
- R0070Tier 2
- R0080Tier 3
Columns
- C0010Amount with Long Term Guarantee measures and transitionals
- C0020Without transitional on technical provisions
- C0030Impact of transitional on technical provisions
- C0040Without transitional on interest rate
- C0050Impact of transitional on interest rate
- C0060Without volatility adjustment and without transitional measures
- C0070Impact of volatility adjustment set to zero
- C0080Without matching adjustment and without all the others
- C0090Impact of matching adjustment set to zero
- C0100Impact of all LTG measures and transitionals
Impact of long-term guarantees measures and transitionals (S.22.01.04.01)
Rows
- R0050Eligible own funds to meet Solvency Capital Requirement
- R0060Tier 1
- R0070Tier 2
- R0080Tier 3
Columns
- C0010Amount with Long Term Guarantee measures and transitionals
- C0020Without transitional on technical provisions
- C0030Impact of transitional on technical provisions
- C0040Without transitional on interest rate
- C0050Impact of transitional on interest rate
- C0060Without volatility adjustment and without transitional measures
- C0070Impact of volatility adjustment set to zero
- C0080Without matching adjustment and without all the others
- C0090Impact of matching adjustment set to zero
- C0100Impact of all LTG measures and transitionals
A worked example
The first of its checks, with simple numbers.
Eligible own funds to meet Solvency Capital Requirement must then be 2,450.
A file that reports 2,450 passes. One that reports 2,550 fails, by 100.
The numbers are illustrative, reported to the unit, so the rounding tolerance does not change the result.
Which returns it applies to
Line4 Check runs it on annual solo (ARS), annual group (ARG) and annual branch (ARB) returns on EIOPA taxonomy 2.10.0. EIOPA applies it to annual branch (ARB), annual solo (ARS), annual ECB solo (AES), annual ECB branch (AEB) and annual group (ARG) returns, as a blocking check.
EIOPA’s own words and formula
In EIOPA’s list of validations, word for word:
The item "Eligible own funds to meet the SCR" reported in S.22.01 - Impact of long-term guarantees measures and transitionals must be equal to the sum of the "Tier I", "Tier II" and "Tier III".
Show the formulaShowHide
EIOPA's formula, for BV63-1. Cells are written as {t: table, r: row, c: column}.
{t: S.22.01.01.01, r: R0050, z: Z0001} = {t: S.22.01.01.01, r: R0060, z: Z0001} + {t: S.22.01.01.01, r: R0070, z: Z0001} + {t: S.22.01.01.01, r: R0080, z: Z0001}BV63-2:
{t: S.22.01.04.01, r: R0050, z: Z0001} = {t: S.22.01.04.01, r: R0060, z: Z0001} + {t: S.22.01.04.01, r: R0070, z: Z0001} + {t: S.22.01.04.01, r: R0080, z: Z0001}Other rules on Impact of long-term guarantees measures and transitionals (S.22.01)
- Impact of long-term guarantees measures and transitionals: values must agree (BV64)Blocking
- Impact of long-term guarantees measures and transitionals: values must agree (BV60)Blocking
- If Impact of long-term guarantees measures and transitionals is reported then rows r0010, r0020, r0050 and r0100 have to be different from 0 (BV690_1)
- If Impact of long-term guarantees measures and transitionals is reported then rows r0010, r0020, r0050 and r0100 have to be different from 0 (BV690_2)
- If Impact of long-term guarantees measures and transitionals is reported then rows r0010, r0020, r0050 and r0100 have to be different from 0 (BV690_3)
- If Impact of long-term guarantees measures and transitionals is reported then rows r0010, r0020, r0050 and r0100 have to be different from 0 (BV690_4)
- If Impact of long-term guarantees measures and transitionals is reported then rows r0010, r0020, r0050 and r0100 have to be different from 0 (BV690_5)
- If Impact of long-term guarantees measures and transitionals is reported then rows r0010, r0020, r0050 and r0100 have to be different from 0 (BV690_6)
Every Solvency II rule on S.22.01