The rule in plain words
The item "Basic solvency capital requirement" reported in Solvency Capital Requirement (SR.25.01) - for undertakings using the standard formula and partial internal model [RFF/MP/RM] must be equal to the sum of the item above. Please note that it should include diversification effects
The headline gives only the template and the kind of check, because the rule is too long to say in a headline. The plain words above say all of it.
EIOPA writes it out as separate checks, one for each table or return it covers. Line4 Check runs six of them (BV254_2-2-3 to BV254_2-2-8), and a failure names the one that failed.
What to do if your return fails it
- 01Open the tables below and find the cells the rule reads.
- 02The check applies only when its first part holds in your return. When it does, the second part must hold too: fix the second part, or correct the first.
- 03EIOPA allows a small rounding difference, worked out from the decimals each value is reported with.
- 04It runs only when your filing indicators mark SR.01.01 and SR.25.01 as reported.
- 05This is a blocking check. A return that fails it is normally rejected, so fix it before you submit.
The cells it reads
Content of the submission (SR.01.01.01.01)
Row
- R0840SR.25.01.01 - Solvency Capital Requirement - for undertakings on Standard Formula
Column
- C0010Reporting status
Content of the submission (SR.01.01.04.01)
Row
- R0840SR.25.01.04 - Solvency Capital Requirement - for groups on Standard Formula
Column
- C0010Reporting status
Content of the submission (SR.01.01.07.01)
Row
- R0840SR.25.01.01 - Solvency Capital Requirement - for undertakings on Standard Formula
Column
- C0010Reporting status
Solvency capital requirement - for undertakings on standard formula: basic solvency capital requirement (SR.25.01.01.01)
Rows
- R0010Market risk
- R0020Counterparty default risk
- R0030Life underwriting risk
- R0040Health underwriting risk
- R0050Non-life underwriting risk
- R0060Diversification
- R0070Intangible asset risk
- R0100Basic Solvency Capital Requirement
Columns
- C0030Net solvency capital requirement
- C0040Gross solvency capital requirement
Solvency capital requirement - for undertakings on standard formula: basic solvency capital requirement (SR.25.01.04.01)
Rows
- R0010Market risk
- R0020Counterparty default risk
- R0030Life underwriting risk
- R0040Health underwriting risk
- R0050Non-life underwriting risk
- R0060Diversification
- R0070Intangible asset risk
- R0100Basic Solvency Capital Requirement
Columns
- C0030Net solvency capital requirement
- C0040Gross solvency capital requirement
Which returns it applies to
Line4 Check runs it on annual solo (ARS), annual group (ARG) and annual branch (ARB) returns on EIOPA taxonomy 2.10.0. EIOPA applies it to annual branch (ARB), annual ECB branch (AEB), annual solo (ARS), annual ECB solo (AES) and annual group (ARG) returns, as a blocking check.
EIOPA’s own words and formula
In EIOPA’s list of validations, word for word:
The item "Basic solvency capital requirement" reported in SR.25.01 - Solvency Capital Requirement - for undertakings using the standard formula and partial internal model [RFF/MP/RM] must be equal to the sum of the item above. Please note that it should include diversification effects.
Show the formulaShowHide
EIOPA's formula, for BV254_2-2-5. Cells are written as {t: table, r: row, c: column}.
if ({t: SR.01.01.01.01, r: R0840, c: C0010, z: Z0001} = [s2c_CN:x60]) then {t: SR.25.01.01.01, r: R0100, c: C0040, z: Z0001, filter: [s2c_dim:AO] = [s2c_AO:x1]} = sum({t: SR.25.01.01.01, r: R0010; R0020; R0030; R0040; R0050; R0060; R0070, c: C0040, z: Z0001, filter: [s2c_dim:AO] = [s2c_AO:x1]}) else true()BV254_2-2-3:
if ({t: SR.01.01.07.01, r: R0840, c: C0010, z: Z0001} = [s2c_CN:x60]) then {t: SR.25.01.01.01, r: R0100, c: C0040, z: Z0001, filter: [s2c_dim:AO] = [s2c_AO:x1]} = sum({t: SR.25.01.01.01, r: R0010; R0020; R0030; R0040; R0050; R0060; R0070, c: C0040, z: Z0001, filter: [s2c_dim:AO] = [s2c_AO:x1]}) else true()BV254_2-2-4:
if ({t: SR.01.01.07.01, r: R0840, c: C0010, z: Z0001} = [s2c_CN:x60]) then {t: SR.25.01.01.01, r: R0100, c: C0030, z: Z0001, filter: [s2c_dim:AO] = [s2c_AO:x1]} = sum({t: SR.25.01.01.01, r: R0010; R0020; R0030; R0040; R0050; R0060; R0070, c: C0030, z: Z0001, filter: [s2c_dim:AO] = [s2c_AO:x1]}) else true()BV254_2-2-6:
if ({t: SR.01.01.01.01, r: R0840, c: C0010, z: Z0001} = [s2c_CN:x60]) then {t: SR.25.01.01.01, r: R0100, c: C0030, z: Z0001, filter: [s2c_dim:AO] = [s2c_AO:x1]} = sum({t: SR.25.01.01.01, r: R0010; R0020; R0030; R0040; R0050; R0060; R0070, c: C0030, z: Z0001, filter: [s2c_dim:AO] = [s2c_AO:x1]}) else true()BV254_2-2-7:
if ({t: SR.01.01.04.01, r: R0840, c: C0010, z: Z0001} = [s2c_CN:x60]) then {t: SR.25.01.04.01, r: R0100, c: C0040, z: Z0001, filter: [s2c_dim:AO] = [s2c_AO:x1]} = sum({t: SR.25.01.04.01, r: R0010; R0020; R0030; R0040; R0050; R0060; R0070, c: C0040, z: Z0001, filter: [s2c_dim:AO] = [s2c_AO:x1]}) else true()BV254_2-2-8:
if ({t: SR.01.01.04.01, r: R0840, c: C0010, z: Z0001} = [s2c_CN:x60]) then {t: SR.25.01.04.01, r: R0100, c: C0030, z: Z0001, filter: [s2c_dim:AO] = [s2c_AO:x1]} = sum({t: SR.25.01.04.01, r: R0010; R0020; R0030; R0040; R0050; R0060; R0070, c: C0030, z: Z0001, filter: [s2c_dim:AO] = [s2c_AO:x1]}) else true()Other rules on Content of the submission (SR.01.01)
- Content of the submission and solvency capital requirement - for undertakings on standard formula: a conditional check (BV254_2-1)Blocking
- Content of the submission and solvency capital requirement - for undertakings on standard formula: a conditional check (BV254_4-2)
- Content of the submission and non-life technical provisions: a conditional check (BV253_2)Blocking
- Content of the submission and solvency capital requirement - for undertakings on standard formula: a conditional check (BV255_2)Blocking
- The item "Total Non-Life obligation" reported in Non-Life Technical Provisions [RFF/MP/RM] must be equal to the sum of the relevant LoB (BV252_2)Blocking
- Content of the submission and solvency capital requirement - market risk: a conditional check (BV256_2)
- Content of the submission and non-life technical provisions: a conditional check (BV251_2)Blocking
- Content of the submission and solvency capital requirement - market risk: a conditional check (BV257_2)
Every Solvency II rule on SR.01.01
Checks like this one, run at the point of submission, are the first step to real-time supervision. Line4 builds SupTech software for financial regulators that runs checks like these as each return arrives.