The rule in plain words
Residential immovable property cannot be more than under construction / development.
EBA checks it for five columns: accumulated impairment, accumulated negative changes in fair value due to credit risk, accumulated negative changes (0050), accumulated negative changes (0080), accumulated negative changes (0110) and accumulated negative changes (0140). That makes five checks. A failure names the one that failed.
How the Line4 Check report words itShowHide
The first of its checks, word for word as the report shows it when it fails. The others read the same, with their own column, row or sheet.
Accumulated negative changes: Residential immovable property <= Of which: under construction / development
What to do if your filing fails it
- 01Open the template below and find the cells the rule reads.
- 02Compare the values in your file. If the first is bigger than it may be, one of them is wrong: check both before you change either.
- 03EBA allows a small rounding difference, worked out from the decimals each value is reported with.
- 04It runs only when your filing indicators mark F 25.02 as reported.
- 05This is a warning. It does not stop the filing on its own, but your authority may ask you to explain it.
The cells it reads
Rows
- 0010Residential immovable property
- 0020Of which: under construction / development
Columns
- 0020Accumulated impairment, accumulated negative changes in fair value due to credit risk
- 0050Accumulated negative changes
- 0080Accumulated negative changes
- 0110Accumulated negative changes
- 0140Accumulated negative changes
A worked example
The first of its checks, with simple numbers.
Under construction / development must then be at least 1,200.
A file that reports 1,200 passes. One that reports 1,100 fails, by 100.
The numbers are illustrative, reported to the unit, so the rounding tolerance does not change the result.
Show the rule as writtenShowHide
EBA's formula, as written out for the first of its checks. Cells are written as {template, row, column, sheet}.
{F_25.02.a,r0010,c0080,} <= {F_25.02.a,r0020,c0080,}The next four:
{F_25.02.a,r0010,c0140,} <= {F_25.02.a,r0020,c0140,}{F_25.02.a,r0010,c0050,} <= {F_25.02.a,r0020,c0050,}{F_25.02.a,r0010,c0110,} <= {F_25.02.a,r0020,c0110,}{F_25.02.a,r0010,c0020,} <= {F_25.02.a,r0020,c0020,}Other rules on F 25.02.a
- Accumulated negative changes, collateral obtained by taking possession other than collateral classified as property Plant and equipment (PP&E) must equal the sum of its three parts (v8081_m)Warning
- Residential immovable property cannot be less than under construction / development (v8083_m)Warning
- Carrying amount in F 25.02.a cannot be less than carrying amount in F 25.02.c (v8080_m)Warning
- Commercial immovable property cannot be more than under construction / development (v8084_m)Warning
- Carrying amount, collateral obtained by taking possession other than collateral classified as property Plant and equipment (PP&E) must equal the sum of its three parts (v8079_m)Warning
- Commercial immovable property cannot be more than land related to commercial real estate corporations (excluding agricultural land) (v8085_m)Warning
- Value at initial recognition in F 25.02.a cannot be less than value at initial recognition in F 25.02.c (v8078_m)Warning
- Commercial immovable property cannot be less than under construction / development (v8086_m)Warning
Every FINREP 9 rule, by template
Checks like this one, run at the point of submission, are the first step to real-time supervision.