The rule in plain words
In column "Total AVA" (0110) of Prudent valuation: core approach - Pre and post diversification (PRUVAL 2) (C32.02.01.01): "Total core approach" (row 0010) must equal the sum of "Portfolios under articles 9 to 17 - total category level post-diversification" (row 0030) and "Portfolios under the fall-back approach" (row 0180).
The headline gives only the template and the kind of check, because the rule is too long to say in a headline. The plain words above say all of it.
What to do if your return fails it
- 01Open the table below and find the cells the rule reads.
- 02Add up the parts in your return and compare the result with the total.
- 03If they differ, a part is missing, a value sits in the wrong cell, or the total is out of date.
- 04The Bank of England allows a small rounding difference, worked out from the decimals each value is reported with.
- 05It runs only when your filing indicators mark C32.02.01 as reported.
- 06This is a warning. It does not stop the return on its own, but your supervisor may ask you to explain it.
The cells it reads
Prudent valuation: core approach - Pre and post diversification (PRUVAL 2) (C32.02.01.01)
Rows
- R0010Total core approach
- R0030Portfolios under articles 9 to 17 - total category level post-diversification
- R0180Portfolios under the fall-back approach
Column
- C0110Total AVA
A worked example
With simple numbers.
Total core approach must then be 2,000.
A file that reports 2,000 passes. One that reports 2,100 fails, by 100.
The numbers are illustrative, reported to the unit, so the rounding tolerance does not change the result.
Which returns it applies to
Line4 Check runs it on the own funds (PRA001) return on Bank of England banking taxonomy 4.1.1. The Bank of England applies it to own funds (PRA001) returns, as a warning.
The Bank’s own words and formula
The plain words above spell out the Bank’s formula, with each cell named from its templates. In the Bank of England’s list of validations, word for word:
[v6337_m];[{t: C32.02.01.01, r: 0010, c: 0110} = {t: C32.02.01.01, r: 0030, c: 0110} + {t: C32.02.01.01, r: 0180, c: 0110}]
Show the formulaShowHide
The Bank of England's formula. Cells are written as {t: table, r: row, c: column}.
{t: C32.02.01.01, r: 0010, c: 0110} = {t: C32.02.01.01, r: 0030, c: 0110} + {t: C32.02.01.01, r: 0180, c: 0110}Other rules on Prudent valuation: core approach - Pre and post diversification (PRUVAL 2) (C32.02.01.01)
- "Total core approach" must equal "Portfolios under articles 9 to 17 - total category level post-diversification" (v6335_m)Blocking
- "Of which: trading book" must not be more than "Total core approach" (v6340_m)Blocking
- Prudent valuation: core approach - Pre and post diversification (PRUVAL 2): a total must equal the sum of its parts (v6342_m)
- "Total category level pre-diversification" must equal the sum of 7 cells (v6344_m)Blocking
- Prudent valuation: core approach - Pre and post diversification (PRUVAL 2): a total must equal the sum of its parts (v6349_m)Blocking
- Prudent valuation: core approach - Pre and post diversification (PRUVAL 2): a total must equal the sum of its parts (v6350_m)Blocking
- "Of which: calculated using the expert based approach" must not be more than "Market price uncertainty" (v6351_m)Blocking
- "Of which: calculated using the expert based approach" must not be less than "Market price uncertainty" (v6352_m)Blocking
Every PRA banking rule on C32.02.01.01
Checks like this one, run at the point of submission, are the first step to real-time supervision. Line4 builds SupTech software for financial regulators that runs checks like these as each return arrives.