The rule in plain words
Loans and advances with an accumulated coverage ratio > 90% cannot be more than loans and advances.
EBA checks it for ten columns, from gross carrying amount (0010) to exposures with forbearance measures (0110). That makes ten checks. A failure names the one that failed.
How the Line4 Check report words itShowHide
The first of its checks, word for word as the report shows it when it fails. The others read the same, with their own column, row or sheet.
Gross carrying amount: Loans and advances with an accumulated coverage ratio > 90% <= Loans and advances
What to do if your filing fails it
- 01Open the template below and find the cells the rule reads.
- 02Compare the values in your file. If the first is bigger than it may be, one of them is wrong: check both before you change either.
- 03EBA allows a small rounding difference, worked out from the decimals each value is reported with.
- 04It runs only when your filing indicators mark F 23.02 as reported.
- 05This is a warning. It does not stop the filing on its own, but your authority may ask you to explain it.
The cells it reads
Loans and advances: additional information on gross carrying amounts (F 23.02)
Rows
- 0010Loans and advances
- 0350Loans and advances with an accumulated coverage ratio > 90%
Columns
- 0010Gross carrying amount
- 0020of which: Exposures with forbearance measures
- 0030Performing
- 0050of which: Exposures with forbearance measures
- 0060Non Performing
- 0070of which: Exposures with forbearance measures
- 0080Unlikely to pay that are not past due or past due <= 90 days
- 0090of which: Exposures with forbearance measures
- 0100Past due > 90 days
- 0110of which: Exposures with forbearance measures
A worked example
The first of its checks, with simple numbers.
Loans and advances must then be at least 1,200.
A file that reports 1,200 passes. One that reports 1,100 fails, by 100.
The numbers are illustrative, reported to the unit, so the rounding tolerance does not change the result.
Show the rule as writtenShowHide
EBA's formula, as written out for the first of its checks. Cells are written as {template, row, column, sheet}.
{F_23.02,r0350,c0010,} <= {F_23.02,r0010,c0010,}The next five:
{F_23.02,r0350,c0050,} <= {F_23.02,r0010,c0050,}{F_23.02,r0350,c0080,} <= {F_23.02,r0010,c0080,}{F_23.02,r0350,c0090,} <= {F_23.02,r0010,c0090,}{F_23.02,r0350,c0100,} <= {F_23.02,r0010,c0100,}{F_23.02,r0350,c0110,} <= {F_23.02,r0010,c0110,}And 4 more, the same formula for the other cells it covers.
Other rules on F 23.02
- Unsecured loans and advances without guarantees: non-financial corporations, SMEs plus non-financial corporations, other than SMEs cannot be less than commercial Real Estate (CRE) loans to SMEs plus commercial Real Estate (CRE) loans to NFCs other than SMEs (v7959_m)Warning
- Loans and advances with an accumulated coverage ratio > 90% cannot be less than the sum of three rows (v7961_m)Warning
- Unsecured loans and advances without guarantees cannot be less than the sum of three rows (v7958_m)Warning
- Loans and advances with an accumulated coverage ratio > 90%: non-financial corporations, SMEs plus non-financial corporations, other than SMEs cannot be less than commercial Real Estate (CRE) loans to SMEs plus commercial Real Estate (CRE) loans to NFCs other than SMEs (v7962_m)Warning
- Unsecured loans and advances without guarantees cannot be more than loans and advances (v7956_m)Warning
- Loans and advances in litigation status: non-financial corporations, SMEs plus non-financial corporations, other than SMEs cannot be less than commercial Real Estate (CRE) loans to SMEs plus commercial Real Estate (CRE) loans to NFCs other than SMEs (v7955_m)Warning
- Loans and advances in litigation status cannot be less than the sum of three rows (v7954_m)Warning
- Loans and advances in pre-litigation status: non-financial corporations, SMEs plus non-financial corporations, other than SMEs cannot be less than commercial Real Estate (CRE) loans to SMEs plus commercial Real Estate (CRE) loans to NFCs other than SMEs (v7953_m)Warning
Every FINREP 9 rule, by template
Checks like this one, run at the point of submission, are the first step to real-time supervision.