The rule in plain words
For on-balance sheet items: these six added up, all for first loss cannot be more than amount:
- Internal ratings-based approach for securitisation positions (sec-IRBA)
- Internal assessment approach
- Standardised approach for securitisations (sec-SA)
- 1250% for positions not subject to any method
- External ratings-based approach for securitisation positions (sec-erba)
- Specific treatment for senior tranches of qualifying NPE securitisations
The template it checks
Detailed information on securitisations (C 14.00)
Column
- 0250AMOUNT
(CR sec details) Detailed information on securitisations by approach (C 14.01)
Column
- 0330FIRST LOSS
Sheets
- 0010Standardised approach for securitisations (SEC-SA)
- 0020External ratings-based approach for securitisation positions (SEC-ERBA)
- 0030Internal ratings-based approach for securitisation positions (SEC-IRBA)
- 00401250% for positions not subject to any method
- 0050Internal assessment approach
- 0060Specific treatment for senior tranches of qualifying NPE securitisations
Show the rule as writtenShowHide
EBA's formula. Cells are written as {template, row, column, sheet}.
sum({C_14.01,,c0330,s0030},{C_14.01,,c0330,s0050},{C_14.01,,c0330,s0010},{C_14.01,,c0330,s0040},{C_14.01,,c0330,s0020},{C_14.01,,c0330,s0060}) <= {C_14.00,,c0250,}Other rules on C 14.00
- A check on detailed information on securitisations (v7370_m)Not run yet
- Detachment point must be between 0 and 1 (column 0251, v7369_m)Warning
- If ul is not zero, own funds requirements before securitisation Kirb must equal el plus ul (v7366_m)Warning
- A check on detailed information on securitisations (v7362_m)Not run yet
- A check on detailed information on securitisations (v7361_m)Not run yet
- A check on detailed information on securitisations (v7360_m)Not run yet
- A check on detailed information on securitisations (v7358_m)Not run yet
- Attachment point of risk sold must be less than detachment point of risk sold (v7357_m)Warning